Equipment Fleet

Semi-industrial mining equipment deployed across four concession sites for optimized gold production.

17

Total Equipment Units

4

Concession Sites

36

Team Members

400g

Daily Target

Equipment Manifest

Excavator XCMG 335

x3

Primary excavation and ore extraction

Dump Truck HOWO/Shacman

x2

Ore and material transport

Wheel Loader XCMG ZL50

x2

Loading and material handling

Bulldozer LiuGong B230

x1

Site preparation and terrain leveling

Hydraulic Hammer

x2

Rock breaking and secondary extraction

Sand Pump 8"

x1

Hydraulic sand and slurry pumping

Water Pump 6"

x1

Water management and dewatering

Toyota Land Cruiser

x2

Management transport and site supervision

Toyota Prado

x1

Executive transport

Motorcycles

x2

Rapid inter-site communication

Deployment Timeline

Months 1-3

Mobilization & Setup

  • Equipment procurement & transport
  • Site preparation
  • Team recruitment & training
Months 4-5

Ramp-Up

  • Progressive production increase
  • Process optimization
  • Quality controls implementation
Months 6-7+

Full Operations

  • Steady-state 400g/day
  • Multi-site rotation
  • Continuous improvement